Footings Complete

With the weather continuing to be wet, we are pleased to have reached the end of the work on the footings. The diagram below shows the past four weeks of work, with the purple segment showing the first concrete to be poured, orange the second, blue the third and this week, the uncoloured segment that forms the atrium, squash court and changing rooms.

 

I haven’t ventured down to the site today, as even by mid-week a canoe was looking like essential kit!

At the start of the week, when the weather was still holding, the continued progress was visible.

 

   

The shape of the surrounding bank is developing nicely and the building works begin to feel more integrated in the wider site. It is hard to believe the frame arrives in just over a week. 

    

Let hope the rain stays off for a while now and the blue skies return. 

 

 

Cat Thompson and Nanci Austin